Dubai Airports' new Modular Data Centre Complex

Congratulations to Dubai Airports for the successful completion of UAE’s first Tier III certified Modular Data Centre Complex (MDCC). 

RED provided design and supervision services for this new build data centre at Dubai International Airport. 

The facility was built as part of a large data centre complex which will provide high-level resilience and availability to support Dubai Airports’ critical operations and to host its private cloud. 

The MDCC was designed, procured, built, manufactured, tested and commissioned in 407 days.  A great achievement for Dubai Airports and an absolute pleasure for us to work with the team!