Confidential Data Centre, London

A 4.8MW Data Centre located in West London that forms the extension of an existing site, this project includes the provision of a new data centre comprising three data halls over two floors with cooling and power located on an external gantry

This phase of the extension consists of two HV streams feeding into 4no. LV streams via 4 No. 3 phase transformers. Additionally the following key mechanical and electrical systems are included:

  • 2No. High Voltage(HV) Mains Switchboards with a further 2No. HV Switchboards for associated secondary power generation.
  • 5No. 2.32MW Generators with associated Neutral Earth Resistors
  • Low Voltage Power supplied via 4No. Switchboards and 4No. Uninterruptible power supplies(UPS).
  • 5No. 1.28MW air cooled chillers
  • 33No. CRAH Cooling units supplying the Data halls.
  • 8No. CRAH Cooling units supplying 4No. UPS rooms.
  • A comprehensive BMS system to monitor and log operation of all individual systems.

RED Solution

RED Engineering Design Limited were the appointed clients Commissioning authority (CxA).

RED has carried out a full Commission-ability review of the design and submitted a comprehensive commissioning implementation plan to ensure a timely and thorough commissioning process is achieved in accordance with the Client’s testing and commissioning requirements. Furthermore RED has been involved in witnessing of testing and commissioning activities and the review of all commissioning documentation including all level 1 to 5 test scripts via the BIM360 portal. RED has managed  the documentation on this portal by logging, reviewing, assessing, and assigning remedial works utilising issue resolution logs. Progress reports and technical reviews have been produced using BIM360 for issue to the client and wider team.

decorative arrow

Key Facts

  • This project sees the addition of three new data halls independent of the main infrastructure
  • RED has carried out a full Commission-ability review of the design and submitted a comprehensive commissioning implementation plan to ensure a timely and thorough commissioning process is achieved.
  • BIM 360 has played a vital role in the project from Design reviews to all Commissioning stages

Client:

Confidential

Location:

UK

Capabilities:

Commissioning Management

Sectors:

Technology

Sub‑sector:

Commissioning Management